Company name
Desarrollo Eólico San Miguel I S.R.L.
Project number
15782-01
Category B projects have potential environmental and/or social impacts and risks that are less adverse than those of a Category A and which are generally limited to the project site, largely reversible and can be mitigated via measures that are readily available and feasible to implement in the context of the operation.
E&S category
B
Country
Costa Rica
Sector
Energy
Status
Proposed
Disclosed date
12/05/2025
Projected date at which a project will be put forward for the Board of Executive Directors’ approval.
Projected board date
03/30/2026
Approval date
N/A
Signed date
N/A
Sponsoring entity
Grupo Empresarial ENHOL S.L. y NAIAD 2012, S.L.
Investment Operations Department Contact
Infrastructure and Energy Division
Investment type
Syndicated amount
N/A
Financing amount
USD $ 46,800,000
Currency
USD
Project scope and objective
The transaction consists of an A/B financing of up to US$46.8 million for the construction of a 43.2 MW wind farm located in Tilarán, Guanacaste.
The project is expected to generate a significant development impact by increasing the installed capacity of renewable energy and contributing to the diversification of Costa Rica’s energy matrix through the addition of wind power. It will also help reduce CO₂ emissions and create new jobs during the construction phase.
For information requests about the project.
Request informationLearn more about how we provide private-sector solutions in the region .
Contact information
For information requests about the project.
Request informationAlternatively, you may also use the following contact information :
Client Contact
PHONE NUMBER
+34 971 713 561
POST OFFICE ADDRESS
CLS Business Center, Sabana, San Jose, Costa Rica
For information requests about the project.
Request informationLearn more about how we provide private-sector solutions in the region .

Early disclosure
For projects with high environmental or social risk an Environmental and Social Strategy (ESS) is prepared early on during the project appraisal and prior to carrying out the environmental and social due diligence (ESDD). The ESS includes the initial E&S risk categorization and a brief description of potential Performance Standards applicable to the project. The ESS for this project is available below. Together with the ESS, IDB Invest also provides access to the client’s preliminary E&S documents that will be reviewed during the ESDD. The client E&S documents for this project can be found under the “CLIENT FILES” section below. Once the environmental and social due diligence is completed, an Environmental and Social Review Summary (ESRS) for the Project will be published on this page.
DESARROLLO EÓLICO SAN MIGUEL - ESTRATEGIA AMBIENTAL Y SOCIAL
204.8 Kb