Company name

RUTAS DEL ESTE S.A.

Project number

15589-01

Category A projects could result in potentially significant environmental and/or social risks and impacts, which are diverse, irreversible, or unprecedented that may extend beyond the boundaries of the actual project site or facilities. In principle, Category A includes projects which have significant impacts on protected or sensitive areas21 and/ or vulnerable groups.

E&S category
tooltip

A

Country

Paraguay

Sector

Transport

Status

Proposed

Disclosed date

06/17/2025

Projected date at which a project will be put forward for the Board of Executive Directors’ approval.

Projected board date
tooltip

12/02/2025

Approval date

N/A

Signed date

N/A

Sponsoring entity

Sacyr S.A | Ocho A S.A.

Investment Operations Department Contact

Infrastructure and Energy Division

Investment type

Syndicated amount

N/A

Financing amount

USD $ 620,000,000

Currency

USD

Project scope and objective

The Ministry of Public Works and Communications of Paraguay (MOPC) has signed an addendum to the PY02 Highway concession agreement with the Special Purpose Vehicle Rutas del Este, made up of Sacyr Concesiones (60%) and Ocho A (40%). Through this addendum, the highway will be expanded to improve connectivity between the capital, Asunción, and other parts of the country, enhance safety, and promote regional development.

 

The project consists of a structuring road network, which includes key works such as the Ypacaraí–Areguá bypasses and a 3.6-kilometer elevated urban expressway with two carriageways and four lanes, connecting Ñu Guasú and Silvio Pettirossi avenues. It also includes two new connections to Route PY02 that are essential for improving connectivity. The first connection begins at kilometer 41 of Route PY02, enhancing accessibility via Ypacaraí, Patiño, Areguá, and Luque. The second connection starts at kilometer 43 and will enhance access through San Bernardino.

 

Both corridors will be part of the Structuring Road Access Network, which will link to Ñu Guasú and Silvio Pettirossi avenues, establishing a more efficient system for entering and exiting the metropolitan area. The proposal also includes the comprehensive operation and maintenance of the road network, ensuring its long-term functionality.

For inquiries, comments and information requests about the project

Request information

Learn more about how we provide private-sector solutions in the region .

Early disclosure

For projects with high environmental or social risk an Environmental and Social Strategy (ESS) is prepared early on during the project appraisal and prior to carrying out the environmental and social due diligence (ESDD). The ESS includes the initial E&S risk categorization and a brief description of potential Performance Standards applicable to the project. The ESS for this project is available below. Together with the ESS, IDB Invest also provides access to the client’s preliminary E&S documents that will be reviewed during the ESDD. The client E&S documents for this project can be found under the “CLIENT FILES” section below. Once the environmental and social due diligence is completed, an Environmental and Social Review Summary (ESRS) for the Project will be published on this page.

RUTAS 2 Y 7 APP TRABAJOS ADICIONALES- ESTUDIO DE IMPACTO AMBIENTAL

10.0 Mb

ROUTES 2 AND 7 PPP ADDITIONAL WORKS - ENVIRONMENTAL AND SOCIAL STRATEGY

163.8 Kb

Environmental and social review

IDB Invest conducts an environmental and social due diligence (ESDD) commensurate with the nature, scale, and stage of the project, and with its level of environmental and social risks and impacts. The ESDD will confirm the project E&S categorization and assess the project with respect to the client requirements in IDB Invest Environmental and Social Sustainability Policy. The results of the ESDD, including any identified gaps are described in the Environmental and Social Review Summary (ESRS) provided below. For projects approved as of 2016, any gaps with respect to IDB Invest's Environmental and Social Sustainability Policy at the time of the ESDD are addressed in the Environmental and Social Action Plan (ESAP) presented below, to comply with the date mentioned above.

OBRAS COMPLEMENTARIAS RUTAS 2-7 - RESUMEN DE LA REVISIÓN AMBIENTAL Y SOCIAL (RRAS O ESRS)

460.8 Kb

OBRAS COMPLEMENTARIAS RUTAS 2-7 - PLAN DE ACCIÓN AMBIENTAL Y SOCIAL (PAAS O ESAP)

307.2 Kb

Client files

This section provides the key environmental and social assessment documents produced by the client for this project.

RUTAS 2 Y 7 APP TRABAJOS ADICIONALES- ANÁLISIS DE IMPACTOS ACUMULATIVOS

471.0 Kb

For inquiries, comments and information requests about the project

Request information

Learn more about how we provide private-sector solutions in the region .

Contact information

For inquiries, comments and information requests about the project

Request information

Alternatively, you may also use the following contact information :

Client Contact

PHONE NUMBER

+595 2 1728 9944

POST OFFICE ADDRESS

Avenida Aviadores del Chaco No. 2050, WTC Torre 3, Piso 20, Asuncion, Paraguay

IDB Invest Contact

PHONE

+1(202)-566-4566

ADDRESS

1350 New York Ave NW, Washington, DC 20005

For inquiries, comments and information requests about the project

Request information